Determinants of rework in building construction projects

Determinants of rework in building construction projects Rework represents the unnecessary effort of redoing a process or activity that is incorrectly implemented the first time. Using a structured questionnaire survey, the causes and costs of rework in 161 Australian construction projects were identified. Respondents were invited to indicate direct and indirect rework costs that would be subsequently combined to produce a total rework cost (TRC) figure. Stepwise linear multiple regression analysis was then used to determine a model that included an optimum mixture of significant variables that contributed or lead to a reduction in TRC for the projects sampled. The research revealed that rework per se can negatively influence project safety. Client initiated changes and ineffective use of information technology by the design professionals were identified as being significant variables contributing to rework occurrence. Contrary to an earlier presupposition, design scope freezing was also identified as being a significant factor that can contribute to rework. http://www.deepdyve.com/assets/images/DeepDyve-Logo-lg.png Engineering Construction & Architectural Management Emerald Publishing

Determinants of rework in building construction projects

Loading next page...
 
/lp/emerald-publishing/determinants-of-rework-in-building-construction-projects-Cg0ewowTwt

References (49)

Publisher
Emerald Publishing
Copyright
Copyright © 2004 Emerald Group Publishing Limited. All rights reserved.
ISSN
0969-9988
DOI
10.1108/09699980410547612
Publisher site
See Article on Publisher Site

Abstract

Rework represents the unnecessary effort of redoing a process or activity that is incorrectly implemented the first time. Using a structured questionnaire survey, the causes and costs of rework in 161 Australian construction projects were identified. Respondents were invited to indicate direct and indirect rework costs that would be subsequently combined to produce a total rework cost (TRC) figure. Stepwise linear multiple regression analysis was then used to determine a model that included an optimum mixture of significant variables that contributed or lead to a reduction in TRC for the projects sampled. The research revealed that rework per se can negatively influence project safety. Client initiated changes and ineffective use of information technology by the design professionals were identified as being significant variables contributing to rework occurrence. Contrary to an earlier presupposition, design scope freezing was also identified as being a significant factor that can contribute to rework.

Journal

Engineering Construction & Architectural ManagementEmerald Publishing

Published: Aug 1, 2004

Keywords: Australia; Construction works; Production costs; Costs