Identifying and prioritizing delay factors in Iran’s oil construction projects

Identifying and prioritizing delay factors in Iran’s oil construction projects Successful implementation of construction projects is one of the crucial factors for the economic development of every country. The main part of the countries’ capital is allocated to civil and infrastructure projects annually, most of which are accomplished with delay. Construction projects are often criticized for overrunning time and budgets. Analyzing the factors causing delay is essential for omitting them and timely implementation of these projects. Due to the importance of oil projects, this study aims to investigate and analyze the factors causing a delay in Iran’s oil construction projects.Design/methodology/approachIn this research, after a broad literature review, using the fuzzy Delphi method, a total of 75 delay factors were identified under 11 major categories of owner, contractor, consultant, equipment, labor, materials, design, contract and contractual relations, laws and regulations, environmental factors, and managerial factors. Then, by using the best-worst method, the factors were prioritized.FindingsThe results showed that sanction, governmental management systems, weak project management by the contractor, technical and managerial weaknesses of the consultant, financial problems and delay in payment by the owner, low efficiency of the equipment, low productivity of the workforce, changes in laws and regulations, inappropriate organizational structure linking to the project, changes in the design, and changes in the price of materials are the most crucial factors causing a delay in Iran’s oil construction projects.Research limitations/implicationsThese findings are expected to have significant contributions to Iran’s oil construction industry in controlling the time overruns in construction contracts.Originality/valueThe main contribution of this study is to develop a comprehensive framework in which, causes of delay in Iran’s oil construction projects are addressed and prioritized. http://www.deepdyve.com/assets/images/DeepDyve-Logo-lg.png International Journal of Energy Sector Management Emerald Publishing

Identifying and prioritizing delay factors in Iran’s oil construction projects

Loading next page...
 
/lp/emerald-publishing/identifying-and-prioritizing-delay-factors-in-iran-s-oil-construction-2OUvS4iJ1b
Publisher
Emerald Publishing
Copyright
© Emerald Publishing Limited
ISSN
1750-6220
DOI
10.1108/ijesm-04-2020-0006
Publisher site
See Article on Publisher Site

Abstract

Successful implementation of construction projects is one of the crucial factors for the economic development of every country. The main part of the countries’ capital is allocated to civil and infrastructure projects annually, most of which are accomplished with delay. Construction projects are often criticized for overrunning time and budgets. Analyzing the factors causing delay is essential for omitting them and timely implementation of these projects. Due to the importance of oil projects, this study aims to investigate and analyze the factors causing a delay in Iran’s oil construction projects.Design/methodology/approachIn this research, after a broad literature review, using the fuzzy Delphi method, a total of 75 delay factors were identified under 11 major categories of owner, contractor, consultant, equipment, labor, materials, design, contract and contractual relations, laws and regulations, environmental factors, and managerial factors. Then, by using the best-worst method, the factors were prioritized.FindingsThe results showed that sanction, governmental management systems, weak project management by the contractor, technical and managerial weaknesses of the consultant, financial problems and delay in payment by the owner, low efficiency of the equipment, low productivity of the workforce, changes in laws and regulations, inappropriate organizational structure linking to the project, changes in the design, and changes in the price of materials are the most crucial factors causing a delay in Iran’s oil construction projects.Research limitations/implicationsThese findings are expected to have significant contributions to Iran’s oil construction industry in controlling the time overruns in construction contracts.Originality/valueThe main contribution of this study is to develop a comprehensive framework in which, causes of delay in Iran’s oil construction projects are addressed and prioritized.

Journal

International Journal of Energy Sector ManagementEmerald Publishing

Published: May 12, 2021

Keywords: Project management; Decision-making; Construction; Fuzzy Delphi method; Multi-criteria decision-making; Delay factors; Best-worst method; Construction projects