Developing a continuous improvement perspective for subcontractor involvement in the industrialised housebuilding supply chain

Developing a continuous improvement perspective for subcontractor involvement in the... <jats:sec> <jats:title content-type="abstract-subheading">Purpose</jats:title> <jats:p>This paper aims to identify those factors, which will improve the collaboration between industrialised housebuilding (IHB) companies and their subcontractors within continuous improvement (CI) programmes. These factors will enhance the supply chain (SC) efficiency and productivity, eliminating obstacles when designing, implementing and managing CI programmes within IHB SC.</jats:p> </jats:sec> <jats:sec> <jats:title content-type="abstract-subheading">Design/methodology/approach</jats:title> <jats:p>An explorative case study with a mixed-method approach was conducted within an IHB SC. To collect data, participant observation and guided interviews were applied. A stakeholder analysis was conducted to structure their guiding principles. A causal loop diagram (CLD) analysis was used to model the effects on and relationships within a SC and their impact on the involvement of subcontractors.</jats:p> </jats:sec> <jats:sec> <jats:title content-type="abstract-subheading">Findings</jats:title> <jats:p>The influences on the stakeholders and the guidelines under which they work are defined. Potential conflicts of interest between stakeholders are identified. A CLD is used to model a better understanding of system behaviour impacting on the relationships within the SC and on subcontractor involvement. The results provide a number of factors that need to be considered when designing, implementing and managing a CI programme.</jats:p> </jats:sec> <jats:sec> <jats:title content-type="abstract-subheading">Research limitations/implications</jats:title> <jats:p>The research suggests better ways to use subcontractors’ specific knowledge of on-site processes such that productivity and efficiency are enhanced. Improvements within the construction supply chain (CSC) will, in the future, not be limited to small improvement gains at company level.</jats:p> </jats:sec> <jats:sec> <jats:title content-type="abstract-subheading">Originality/value</jats:title> <jats:p>This paper extends the body of knowledge in CSC management by revealing factors important for designing, implementing and managing CI programmes, which enables the successful involvement of subcontractors in CI on SC level.</jats:p> </jats:sec> http://www.deepdyve.com/assets/images/DeepDyve-Logo-lg.png Supply Chain Management: An International Journal CrossRef

Developing a continuous improvement perspective for subcontractor involvement in the industrialised housebuilding supply chain

Supply Chain Management: An International Journal , Volume ahead-of-print (ahead-of-print) – Nov 4, 2020

Developing a continuous improvement perspective for subcontractor involvement in the industrialised housebuilding supply chain


Abstract

<jats:sec>
<jats:title content-type="abstract-subheading">Purpose</jats:title>
<jats:p>This paper aims to identify those factors, which will improve the collaboration between industrialised housebuilding (IHB) companies and their subcontractors within continuous improvement (CI) programmes. These factors will enhance the supply chain (SC) efficiency and productivity, eliminating obstacles when designing, implementing and managing CI programmes within IHB SC.</jats:p>
</jats:sec>
<jats:sec>
<jats:title content-type="abstract-subheading">Design/methodology/approach</jats:title>
<jats:p>An explorative case study with a mixed-method approach was conducted within an IHB SC. To collect data, participant observation and guided interviews were applied. A stakeholder analysis was conducted to structure their guiding principles. A causal loop diagram (CLD) analysis was used to model the effects on and relationships within a SC and their impact on the involvement of subcontractors.</jats:p>
</jats:sec>
<jats:sec>
<jats:title content-type="abstract-subheading">Findings</jats:title>
<jats:p>The influences on the stakeholders and the guidelines under which they work are defined. Potential conflicts of interest between stakeholders are identified. A CLD is used to model a better understanding of system behaviour impacting on the relationships within the SC and on subcontractor involvement. The results provide a number of factors that need to be considered when designing, implementing and managing a CI programme.</jats:p>
</jats:sec>
<jats:sec>
<jats:title content-type="abstract-subheading">Research limitations/implications</jats:title>
<jats:p>The research suggests better ways to use subcontractors’ specific knowledge of on-site processes such that productivity and efficiency are enhanced. Improvements within the construction supply chain (CSC) will, in the future, not be limited to small improvement gains at company level.</jats:p>
</jats:sec>
<jats:sec>
<jats:title content-type="abstract-subheading">Originality/value</jats:title>
<jats:p>This paper extends the body of knowledge in CSC management by revealing factors important for designing, implementing and managing CI programmes, which enables the successful involvement of subcontractors in CI on SC level.</jats:p>
</jats:sec>

Loading next page...
 
/lp/crossref/developing-a-continuous-improvement-perspective-for-subcontractor-0kpm3UQfh6
Publisher
CrossRef
ISSN
1359-8546
DOI
10.1108/scm-12-2019-0435
Publisher site
See Article on Publisher Site

Abstract

<jats:sec> <jats:title content-type="abstract-subheading">Purpose</jats:title> <jats:p>This paper aims to identify those factors, which will improve the collaboration between industrialised housebuilding (IHB) companies and their subcontractors within continuous improvement (CI) programmes. These factors will enhance the supply chain (SC) efficiency and productivity, eliminating obstacles when designing, implementing and managing CI programmes within IHB SC.</jats:p> </jats:sec> <jats:sec> <jats:title content-type="abstract-subheading">Design/methodology/approach</jats:title> <jats:p>An explorative case study with a mixed-method approach was conducted within an IHB SC. To collect data, participant observation and guided interviews were applied. A stakeholder analysis was conducted to structure their guiding principles. A causal loop diagram (CLD) analysis was used to model the effects on and relationships within a SC and their impact on the involvement of subcontractors.</jats:p> </jats:sec> <jats:sec> <jats:title content-type="abstract-subheading">Findings</jats:title> <jats:p>The influences on the stakeholders and the guidelines under which they work are defined. Potential conflicts of interest between stakeholders are identified. A CLD is used to model a better understanding of system behaviour impacting on the relationships within the SC and on subcontractor involvement. The results provide a number of factors that need to be considered when designing, implementing and managing a CI programme.</jats:p> </jats:sec> <jats:sec> <jats:title content-type="abstract-subheading">Research limitations/implications</jats:title> <jats:p>The research suggests better ways to use subcontractors’ specific knowledge of on-site processes such that productivity and efficiency are enhanced. Improvements within the construction supply chain (CSC) will, in the future, not be limited to small improvement gains at company level.</jats:p> </jats:sec> <jats:sec> <jats:title content-type="abstract-subheading">Originality/value</jats:title> <jats:p>This paper extends the body of knowledge in CSC management by revealing factors important for designing, implementing and managing CI programmes, which enables the successful involvement of subcontractors in CI on SC level.</jats:p> </jats:sec>

Journal

Supply Chain Management: An International JournalCrossRef

Published: Nov 4, 2020