Construction productivity assessment on Brock Commons Tallwood House
Abstract
<jats:sec>
<jats:title content-type="abstract-subheading">Purpose</jats:title>
<jats:p>The purpose of this paper is to improve the understanding of the impact of mass timber construction methods on construction performance through the successful delivery of the first-of-a-kind tall wood building, Brock Commons Tallwood House (Tallwood House). This paper is one of a set of papers examining the project; companion papers describe innovations used during the mass timber design and construction processes.</jats:p>
</jats:sec>
<jats:sec>
<jats:title content-type="abstract-subheading">Design/methodology/approach</jats:title>
<jats:p>A mixed-method, longitudinal case study approach was used in this research project to investigate and document the Tallwood House project. Quantitative data were collected to perform the following analysis: hook time, the variability of productivity and schedule reliability. Members of the research team observed construction progress, meetings and decision-making, conducted periodic interviews and reviewed project artifacts.</jats:p>
</jats:sec>
<jats:sec>
<jats:title content-type="abstract-subheading">Findings</jats:title>
<jats:p>The research presented in this paper is the culmination of a longitudinal study aimed at studying the innovation process on a project where radical innovations of structural systems were developed. Prefabrication, combined with the use of a virtual design and construction (VDC) model for planning and fabrication and early collaboration with trades, construction managers and consultants, increased the labor productivity of the on-site erection of the mass timber structural components and envelope panels and expedited the construction schedule.</jats:p>
</jats:sec>
<jats:sec>
<jats:title content-type="abstract-subheading">Originality/value</jats:title>
<jats:p>This paper details an in-depth investigation into the construction productivity for a unique building project and lessons learned. The case study chosen is the construction of Tallwood House at the University of British Columbia. Tallwood House was the tallest mass-timber hybrid building in the world at the time of its construction.</jats:p>
</jats:sec>